Remark Calendar plan total does not match the sumwithin the document · p. 69 9,3 + 554,6 ≠ 570,0
In year 10, overburden removal is 9.3 thousand m³ and extraction 554.6, together 563.9. The “Total” row says 570.0, as in years 1 to 9.
«Вскрышные 9,0 … 9,0 9,3»
«Добычные 561,0 … 561,0 554,6»
«Всего 570,0 … 570,0 570,0»p. 69 · table 2.6.1 · last column is year 10
Remark Water consumption in the text and in the table does not matchwithin the document · p. 86 3 880 + 10 ≠ 1 500
The text gives 1.5 thousand m³ per year for dust suppression and firefighting. Table 6.4.1 on the same page gives 3,880 and 10 m³. Which value is the design value?
«Расход воды на пылеподавление карьера и пожаротушение составит 1,5 тыс.м3/год.»p. 86 · section 6.4
«2 Пылеподавлен м3 27,72 1 27,72 3880 8»p. 86 · table 6.4.1
«3 Пожаротушени м3 10 1 10 10 1»p. 86 · table 6.4.1
Met Mine works plan term within the limitagainst a code · pp. 7, 12 10 years ≤ 10 years
The plan covers 10 years, and the minerals extracted are common minerals. For them the Instruction sets a 10-year limit.
«…в соответствии с «Инструкцией по составлению плана горных работ» … № 351 на срок на 10 лет.»p. 7
«Координаты участка добычи с контуром запасов общераспространённых полезных ископаемых»p. 12 · section 1.2.1
Not checked Whether resource and reserve contours are accounted foragainst a code · p. 54 appendices not in the file
Page 54 refers to reserve calculations in text appendices 25–34. The published PDF does not include those appendices: the file ends on p. 105 with the list of sources. So the report does not mark the requirement “met” and names the missing data.
«Расчеты к определению балансовых запасов и объемов вскрышных пород приведены в текстовых приложениях 25-34»p. 54